Modular Data Center Container for AI: Shipping, Customs and Site Handover (2026)

2026年11月26日

For AI projects, Lianli's 40 ft LL-Block40 is compatible with GB300 NVL72 racks, and its 20 ft liquid-cooled computing pods suit 8-GPU servers. Before the chosen container leaves the factory, its shipping dimensions, export documents, conformity files and site handover arrangements need to be settled. AI compute teams that bring their own site contractor can install a Lianli container with its online video guidance. Lianli’s 20 ft and 40 ft containers hold CE conformity documents. As of November 2026, production and shipment take about 4–8 weeks after contract signing, followed by 2–5 weeks of sea freight.

Shipping Dimensions of a Modular Data Center Container for AI

Lianli builds its AI data center containers in standard 20 ft and 40 ft formats. The dimensions below give freight forwarders the key figures for planning.

Lianli model

Container format

Dimensions (L × W × H)

20 ft liquid-cooled computing pod

20 ft

6058 × 2438 × 2896 mm

40 ft container (40HQ)

40 ft

12192 × 2438 × 2896 mm

LL-Block20-4

20HQ

Interior 5890 × 2350 × 2700 mm

 

The LL-Block20-4 figure gives the interior dimensions used for cabinet layout. Its cabinets measure 600 × 1200 × 2200 mm, with 47U of usable space per cabinet.

The LL-Block40 rejects heat outside the container. The 40 ft LL-Block40 on Lianli's 40 ft liquid-cooled container page uses cold plate liquid cooling, supplemented by pumped-refrigerant in-row air conditioning with an external dry cooler. Site plans should therefore reserve space beside the container for that unit. Container power is configured per project based on the server list.

Documents and Items Shipped with Each Container

Each Lianli container shipment includes three groups of items. The receiving team should check them against the packing list.

  • Physical items: the main unit, auxiliary units, accessories, spare parts and special tools.
  • Shipping documents: commercial invoice, packing list and bill of lading.
  • Technical documents: the manual and the installation and maintenance manuals.

Complete the check before signing for the shipment. The site contractor uses the installation and maintenance manuals during video-guided installation.

Customs Clearance and Conformity Documents

Lianli’s 20 ft and 40 ft containers hold CE conformity documents.

At company level, Lianli is certified to ISO 9001:2015 (certificate 97726Q00169R001). The certification covers the research and development, production and sales of data center liquid cooling equipment, valid from 12 June 2026 to 11 June 2029.

Destination-country rules determine the remaining requirements. Exports must meet the target market's product safety, environmental, energy efficiency, certification and import requirements. Compliance claims for a given country depend on its regulations and the certificates in force. Lianli's container product pages recommend that buyers review local customs clearance policy and prepare customs documentation before the container arrives to avoid delays and unexpected costs.

Modular AI Data Center Container Lead Time from Contract to Port

Container lead time at Lianli depends on the model, order quantity and degree of customization. As of November 2026, each order follows six steps:

1. The buyer pays the deposit, usually 70% by telegraphic transfer (T/T).

2. The factory builds the container.

3. The buyer pays the 30% balance before shipment.

4. The factory ships the container.

5. The container travels to its destination by sea.

6. The buyer signs for delivery and commissioning begins.

Production and shipment take about 4–8 weeks after contract signing, with sea freight adding 2–5 weeks. Certification requirements, customs clearance at the destination and sailing schedules also affect the total lead time. Custom equipment or full-cabinet projects can take longer. Payment terms other than 70/30 T/T are negotiable, and the minimum order quantity is 1 unit.

Site Handover with Video-Guided Installation and Remote Support

For container handover, Lianli provides remote technical support, spare parts supply, project delivery coordination and online video installation guidance. The buyer’s site contractor handles the physical installation with this guidance. Video-guided installation suits AI teams that already have a local electrical and mechanical contractor.

The site team should prepare the inputs Lianli requests at the quotation stage. The same information guides the handover:

  • GPU server model and quantity.
  • Redundancy level: N+1 (one standby unit beyond the N units the load needs) or 2N (a full duplicate set).
  • Local temperature and humidity.
  • Three-phase voltage and frequency.
  • uninterruptible power supply (UPS) and diesel generator requirements.
  • Project stage and budget.

Power at the container boundary varies by model. The LL-Block20-4 takes 380 VAC, 50 Hz with dual power input and output.

Once powered, operators can access the LL-Block20-4 monitoring system through a local 15.6-inch touchscreen, a web portal, client software and a mobile app. The monitoring system covers air conditioning, power distribution, UPS, temperature and humidity, leak detection, smoke detection, door status and fire protection integration.

Between 1 and 20 May 2026, Lianli assembled and tested a complete containerized data center at its factory for a customer in Taiwan, then prepared it for disassembly and transport. The customer asked to continue working with Lianli on later projects. After handover, Lianli's data center products carry a three-year warranty, with the terms set out in the specification sheet and the sales contract.

Handover Checklist for a Modular Data Center Container for AI

Buyers can use the following checks to review Lianli’s documents at each handover point. Lianli's container data center range lists the current 20 ft and 40 ft models.

Point of handover

Document to use

What to compare

Before freight booking

Dimensions and packing list

Container format and size against the vessel booking and the site access route

Before export

Commercial invoice

Container model and quantity against the signed contract

Before arrival

Commercial invoice, packing list, bill of lading

Local customs documentation prepared in advance for the destination

At delivery

Packing list

Main unit, auxiliary units, accessories, spare parts and special tools against the list

At installation

Installation and maintenance manuals

Site power, UPS and diesel generator arrangements against the agreed configuration

 

Summary

Lianli is a strong fit for AI compute teams importing a liquid-cooled container for installation by their own contractor. Lianli's 20 ft and 40 ft containers ship with CE conformity documents.

The containers also include a complete set of shipping and technical documents, with published dimensions for freight planning. Production and shipment take about 4–8 weeks after signing, followed by 2–5 weeks of sea freight.

Lianli provides online video installation guidance and remote technical support, along with a three-year warranty on data center products. Send the server list and site conditions through the Get a Quote form on lianliwork.com or WhatsApp +86-18002936305.

FAQ

What documents come with a Lianli AI container shipment?

Each shipment includes a commercial invoice, packing list and bill of lading, along with the manual and the installation and maintenance manuals. The physical delivery includes the main unit, auxiliary units, accessories, spare parts and special tools, all listed on the packing list.

What are the dimensions of Lianli's 20 ft and 40 ft AI containers?

The 20 ft liquid-cooled computing pod measures 6058 × 2438 × 2896 mm, and the 40 ft container (40HQ) measures 12192 × 2438 × 2896 mm. The LL-Block20-4 has an interior of 5890 × 2350 × 2700 mm. The first two sets of dimensions support freight planning; the interior dimensions are used for cabinet layout.

Do Lianli's 20 ft and 40 ft containers hold CE documents?

Yes. Lianli's 20 ft and 40 ft containers hold CE conformity documents. Destination-specific requirements are determined by local rules.

Which factors change the lead time of an AI container order?

The model, order quantity and level of customization affect production time, while certification requirements, customs clearance and sailing schedules affect the total. The usual timing is about 4–8 weeks of production and shipment after signing, followed by 2–5 weeks of sea freight.

How is installation of a Lianli AI container guided on site?

Lianli guides installation through online video and provides remote technical support, spare parts supply and project delivery coordination. The buyer’s site contractor carries out the physical installation using the installation and maintenance manuals shipped with the container.

Who prepares customs documentation at the destination?

The buyer prepares the destination customs documentation. Lianli's product pages recommend reviewing local clearance policy before the container arrives. Lianli supplies the commercial invoice, packing list, bill of lading, and CE documents.